RETANOL® INDESTRA 100 CONCENTRATE

RETANOL® INDESTRA 100 CONCENTRATE

The specialist for industrial floors withstands every hardness test and achieves strengths up to CT-C70-F9. It is ideal for bonded screeds in accordance with DIN 18560-7/BS 8204* with high surface strength requirements and wear resistance up to A6.

*UK only

  • Compressive and flexural strength

    up to CT-C70-F9
  • Foot traffic

    after 1 day
  • Normal site traffic

    after 2 days
  • Commisioning UFH

    after 4 days
  • Surface strength

    ≥ 1,5 N/mm²
  • Shrinkage

    SW 2 (SW 1 with Agent I®)
  • Energy efficiency class

    EC 3
  • Certification

    Emission-tested (TÜV Rheinland), EC1 Plus according to Emicode
  • Minimum nominal thickness 10 kN/m²: from 70 mm
  • Area load: up to 20 kN/m²
  • Wear resistance: up to A6
DOSAGE & CEMENT QUANTITY
MIXING INSTRUCTIONS
Notes
POINT LOADS INFORMATIONS
FURTHER PRODUCT FEATURES
Downloads

DOSAGE

Compressive strengthCT-C40-F6CT-C50-F7CT-C60-F8CT-C70-F9
Dosage400 ml 400 ml 450 ml 500 ml 
Cement quantity62,5 kg 75 kg 75 kg 75 kg 
Wear resistance≥ A12≥ A9/(A8 to A6)*≥ A9/(A8 to A6)*≥ A9/(A8 to A6)*

*CEM I 42.5 R/N and smoothing of wings

  • Do not exceed the maximum dosage of 600 ml.
  • The specifications refer to a standard mixing vessel with a net capacity of 200 litres and a filling quantity of approx. 320 kg of screed gravel.
  • The specification "after the X. Day" does not include the day of installation.
  • The strength class depends on the quality of the screed gravel used.

MIXING INSTRUCTIONS

  1. Shake the container well to mix the Retanol® Indestra 100 Concentrate additive to a consistent colour before use, and then shake as required throughout the installation to maintain the consistency of the liquid (every 30 mins).
  2. Fill half of mixing vessel with 0-4 mm screeding sand (60-70% fine grains up to 2 mm in diameter, and 30-40% coarse grains greater than 2 mm in diameter).
  3. Add Retanol® Indestra 100 Concentrate to the first mixing water (usually 5-10 litres), then fill the machine completely.
  4. Gradually add the required amount of residual water until a stiff-plastic consistency is achieved.
  5. Let the screed mix for a full 2 minutes.

SAND, WATER, CEMENT

  • Grading curve: Sand must be according to DIN 1045-2 A/B / BS 13892-2*, for the production of screed concrete, Körnungsbereich 0–8 mm
    • 0-4 mm: For bonded screed with nominal thicknesses < 20 mm
    • 0-8 mm: For bonded screed with nominal thicknesses ≥ 20 mm
  • W/C value: Min 0.4 max. 0.6
  • Cement: Use of cement according to PCT cement release list
  • ≥ C50-F7: 75 kg cement grade 42.5 R/N according to PCT cement release list
  • Wear resistance classes A8 to A6: 75 kg CEM I-Cement of grade 42,5 R/N

*UK only

PROCESSING INSTRUCTIONS

  • Working time: 45 minutes
  • Finishing time: 60 minutes
  • Outside temperature: +5 °C to +28 °C for screed, environment and substrate
  • Do not mix with other screed additives
  • Never reactivate screed that has already set with water

Airing

  • If the air humidity is 55 % or higher, ventilate 3-4 times a day for 20-30 minutes 24 hours after screed installation in order to achieve readiness for covering.
  • If the humidity is below 55%, contact PCT technical support to avoid cupping etc.

CM MEASUREMENT

  • A screed with Retanol® Indestra 100 Concentrate does not have a defined readiness for covering and is therefore assessed with regard to its residual moisture in accordance with the measurement and assessment standards of DIN 18560/BS 8204*.
  • In this case, PCT Chemie and the Retanol® specialist company assume no responsibility for the readiness for covering.
  • The CM measurement is therefore part of the floor layer's inspection obligation and is carried out by him.

*UK only

Protective instructions during and after installation

  • We recommend our PROTEC-ES/SP product to protect against drying out too quickly, depending on the floor covering. We recommend consulting the PCT technical support team.
  • Protect the screed against rapid drying of the surface due to draughts, sunlight and low humidity.
  • Large window fronts and floor-level glass façade areas should be darkened if necessary.
  • Cover screeds in outdoor areas or enclose areas to be covered. Contact PCT technical support if screed is to be laid outdoors.

SPECIAL INSTRUCTIONS

Wear resistance classes A8 to A6:

  • For A9: The screed surface must be levelled by machine.
  • For A8, A7, and A6: Additional sash smoothing with a powerful machine weighing at least 80 kg.
  • For wear resistance classes below A9, we recommend carrying out an initial inspection.

 

Hard material scattering:

  • In principle, all hard materials regulated according to DIN 1100/BS 20290* can be used.
  • Carry out your own tests in advance to check the compatibility of Retanol® Indestra 100 Concentrate and the binder used for the bedding.
     

Bonded screeds:

  • Bonding Course: The bonding course ZE from PCT Chemie must be used to create the bond.
  • Curings: The substrate must not be treated with curings to ensure adhesion.

*UK only

POINT LOADS INFORMATIONS

Area load
Point load
5,0 kN/m2
4,0 kN
7,5 kN/m2
6,0 kN
10,0 kN/m2
8,0 kN
15,0 kN/m2
10,0 kN
20,0 kN/m2
15,0 kN
Flexuale strength ≥ F6 45 mm60 mm75 mmn/an/a
Flexuale strength ≥ F840 mm55 mm70 mm75 mm (Separating layer)85 mm (Separating layer)
  • For nominal thicknesses below 5 kN/m², see point loads information Retanol® Xtreme.
  • Specifications, unless otherwise defined, as minimum nominal thickness (without UFH) or minimum pipe cover (with UFH).

FURTHER PRODUCT FEATURES

  • Shrinkage can be further reduced in combination with Agent I®
  • Density approx. 2,000 to 2,200 kg/m3
  • Thermal conductivity approx. 2.0-2.4 lambda
  • Better processing and lower peel resistance
  • Minimally effected by building climate conditions
  • Reduction of air content
  • Start ventilation after 1 day
  • 80-90 % of final strength 3 days after installation
  • Moisture protection for at least 4 months
DOSAGE & CEMENT QUANTITY

DOSAGE

Compressive strengthCT-C40-F6CT-C50-F7CT-C60-F8CT-C70-F9
Dosage400 ml 400 ml 450 ml 500 ml 
Cement quantity62,5 kg 75 kg 75 kg 75 kg 
Wear resistance≥ A12≥ A9/(A8 to A6)*≥ A9/(A8 to A6)*≥ A9/(A8 to A6)*

*CEM I 42.5 R/N and smoothing of wings

  • Do not exceed the maximum dosage of 600 ml.
  • The specifications refer to a standard mixing vessel with a net capacity of 200 litres and a filling quantity of approx. 320 kg of screed gravel.
  • The specification "after the X. Day" does not include the day of installation.
  • The strength class depends on the quality of the screed gravel used.
MIXING INSTRUCTIONS